Project Backlog
TAM Digital Platform Strategy
& Website Transformation
Project Epics
All
TAM Website Transformation
5 sprints · 36 stories · ~89 pts
EP-01
Technical Discovery
Sprint 1 · 9 stories · 28 pts
EP-02
Digital Look & Feel
Sprint 2 · 4 stories · 10 pts
EP-03
UX/UI & Architecture
Sprint 2–3 · 9 stories · 39 pts
EP-04
Development & Integrations
Sprint 3–4 · 9 stories · 38 pts
EP-05
Testing & Launch
Sprint 5 · 5 stories · 15 pts
Backlog View
Estimated total duration: 8–10 weeks · 2-week sprints · Adjust based on TAM team availability for reviews and content delivery.
S1
S2
S3
S4
S5
Recommended setup for creating this project in Jira Software with a Scrum plan.
| Field | Recommended Value | Notes |
|---|---|---|
| Project type | Scrum (Software) | Enables Scrum board and sprints |
| Project key | TAM | Prefix for all tickets: TAM-1, TAM-2… |
| Sprint duration | 2 weeks | Configured in Board Settings |
| Epics | EP-01 to EP-05 | Create before stories; assign color per epic |
| Story Points | Fibonacci: 1, 2, 3, 5, 8, 13 | Standard Jira “Story Points” field |
| Priority | High / Medium / Low | Native Jira field |
| Issue type | Epic, Story, Task, Bug | Subtasks for internal breakdown |
| Board columns | To Do → In Progress → In Review → Done | Board Settings → Columns |
| Acceptance criteria | Text field on each Story | Use template: Given / When / Then |
| Labels | frontend, backend, design, integration, SEO | Enables cross-filter queries |
| Definition of Done | Reviewed + approved by TAM + no blocking bugs | Configure in Board Settings |
| Target velocity | ~17–18 pts per sprint | Adjust after Sprint 1 retrospective |